SpecificationsThe following document is a list of specifications given to any potential customer by the Allen's that gives a flavour of the work and materials that went into making an Allen's hull. It's dated 1992 so that gives some idea to the prices being asked LES ALLEN & SONS"Oldbury "Style Narrowboats Superb traditionally styled narrowboats with the design having formulated from many years of experience building narrowboats. Development is a continuous process and we are constantly honing the finer points of design. The specification set out below can be modified as the client's behest as necessary, but if we think you want something stupid, we will tell you! STEELWORK SPECIFICATION Hull: Bottom framing and knees: 75 x 50 x 6mm rolled steel angles at 750mm centres with 150 x 75mm inverted channel section running longitudinally down the centre of the base plate forming a strong keelson. Base plate is 10mm as standard but can be increased to 12mm at extra cost of £8.00 per foot run of hull. Hull sides are of 6mm m .s plate. Gunwhales: 125 x 10mm welded to sides. N.B. Folded gunwhales favoured by so many fabricators are cheaper but not good to walk on whereas welded gunwhales give a wide flat surface. Guards: Two 2" x 0.5" square guards running all around the boat with two extra ones at the fore end. Continuously welded on the top and stitched underneath. Counters normally have two colours - three guards but three colours and four guards may be necessary on deep sided shallow draughted boats. Foredeck: Full traditional style with steel rolled end cants, two fender eyes, large 'T' stud, steel deck lid with heavy trad hinges and a substantial head ledge. Self draining gas locker is normally situated under the fore deck with storage for at least 4 13Kg propane bottles. In longer fore deck than standard (54"), solid fuel storage can also be incorporated (at extra cost). Front cockpit deck: 5mm. steel self draining on all but tug style boats which must have a sump and auto. Bilge pump (at extra cost). This can be also done if the boat is deep draughted and you wish to keep the maximum freeboard. Water tank: We will not construct integral water tanks under the fore deck - they are unhealthy! It is difficult when they are new to paint them properly and almost impossible afterwards. The paint has a maximum life of two years. If the seal on the lid is not perfect, it allows contaminated water in - not nice. So we fit separate tanks which are hot dip galvanised after manufacture. They cost more, but are worth it. Capacity is about 125 - 150 gallons, but can be increased if the fore deck height and/ or length permits. The filler is a 1.5" raised galvanised cap located on the cockpit deck. Water tanks can be located in other parts of the vessel Counter: There are two stern shapes available - "Josher "and "Woolwich". The former tapers to a half round, whereas the latter tapers to an ellipse. Steel deck, cants and block. Traditional dollies. Four fender eyes. Weedhatch: Quick release with anti - cavitation plate Swim: As long as you would like it. Rudder: Strong rudder in 12mm, plate with 40mm stock through a 4 " diameter elum tube and a squared Swan's neck fitting. 40mm solid bar Swan's neck turned to take a brass tiller extension secured by a brass tiller pin. Skeg : 100 x 25mm solid flat with 75 x 50mm steadying bar and thick walled rudder cup. Diesel Tank: Across the counter as standard. This design will usually give 60 gallons capacity but this will vary with draught, counter shape, hull side height etc. Raised filler and brass flameproof vent in counter block. Fuel tanks may be located in other parts of the vessel (at extra cost). Engine bearers: Constructed of heavy rolled channel of a height to suit the engine chosen, suitably gusseted where necessary. An integral drip tray is formed underneath. Cabin: Of 5mm plate with integral cants (handrails). Roof beams are of 50 x 25 x 5mm channel with timber let into them to provide a fixing for internal lining. Drilled steel lining attachments provided as required. Steel bulkheads front and rear with steel doors and a ply or steel slide at rear. Front doors, side doors and hatches, pigeon boxes are available at extra cost. Window and vent apertures cut as required. Traditional, semi-trad or cruiser style stern as desired. STEELWORK PRICES - standard steelwork The Building of an Allen Boat in Words and PicturesYou would probably have come to the decision by looking at other boats or by recommendation that an Allen boat was the boat for you.
You are shown around probably by Bob discussing as you go the type of boat you want. The visit ends in the shed and you strike the deal with a small deposit, Bob giving you some idea of how long you will have to wait. The above spec's sheet is given to you and you leave to hunt for the engine you will need for the project. Months go by (in it's hey day a wait of twelve months or more was not uncommon.) then suddenly you are asked to come to the yard, told that the steel is to be ordered and can you supply the money for the steel.
The base plate is now cut to the reveal the length of swim at the stern. Both sections of metal remaining where they are cut, the off cut section to be later lifted to form the bottom of the counter section.
The gun whales are welded onto the top edge of the sides and all the time the boat is being kept straight and square by the bracing. Much work is done to finish off the stern and bow details including the decks at both ends. The rubbing strakes are fitted to the hull; it's a long and arduous job especially when the strakes are bent around the counter. The rubbing strakes are straightened by welding onto the outside of the hull straight lengths of metal edge on and with the use of a tool that has a threaded puller, the strakes are pulled into line.
The water tank is loaded into the boat and then the boat is jacked up and placed on rollers ready for its first trip. It's pulled out of the shed by the yard's JCB far enough to lift the engine into the boat before the hull is pushed back into the shed.
Bob spends hours welding what must be miles of continuous welds that seals the hull and finishes the job, whilst John removes the bracing and spends hours on an angle grinder smoothing all the visible welds to give the hull that finished look. The boat is then pulled out of the shed and parked in the yard on railway sleepers the shell is then left to rust, something that appears odd to the stranger. But like every thing else it was the right thing to do, as the rust breaks down the hard skin of metal known as mill scale. This hard skin is on the surface of the plates and was caused by the rolling process in the steel works. Paint will not adhere properly to mill scale so it had to be removed by the rusting process, if it did not rain, endless cold pots of tea were emptied over the boat. If still the boat didn't rust acid was painted onto the steel to promote the rusting. The best process to prepare the surface once the rust had done its job was to have the boat sandblasted. The Allen's always liked to sand blast the boats but this was always a dirty job that covered the whole area with a film of sand, it became more difficult to do in a world becoming more correct. Once blasted the hull was blacked on the outside and the inside of the hull and both surfaces of the cabin painted with under coat. Finally with all steel work finished inside and out the day of the launch comes. In the early days all the boats were launched side ways using chocks and wedges and the force of gravity. This was very spectacular and the brothers where always grateful if the owner was not present just in case anything went wrong. Latterly a crane was used the driver of which swung fully length boats over the top of the sheds with ease. Launch day was always a long day, firstly all the boats in one of the arms were moved into the main canal usually blocking the line. Then the crane was position carefully so as not to collapse a brick culvert that ran across the yard and then the lift began. The brothers were always happy when the boat hit the water as when it was dangling on the end of the chain it was still their responsibly, as soon as it hit the water it was over to the owner. They were always the first into the boat to see if there were any leaks and it was always joked that they used to leave one secti on of weld undone until the final bill had been paid, and that they were just checking that one of them had completed the weld. As soon as a boat was pulled out of the shed to be parked in the yard or onto the back of a lorry to be fitted out elsewhere it was never long before the base plate of the next boat was put down and the process repeated. Sometimes more then one boat was built; one being in the shed where a steel deck existed onto which the base plates could be levelled easily whilst the others would be built in the open on old railway sleepers. Other boats being re bottomed or repaired would be weaved into the schedule, the work never ceasing even when one the brothers went on his annual fortnights holiday. All the time around the Allen's the owner's of the boats at the yard were busily fitting out their boats using all the facilities at the yard. A real boat dock sadly gone. Back to page 2 of The Allen Register | On to page 4 of The Allens Register | |||||||||||||||||||||||||||||||||
|